Specifies the unit cost at one unit of measure for the machine center. The unit of measure is defined in the assigned work center.
Unit costs differ from direct unit costs in that the indirect costs have already been included in the unit cost calculation. The program calculates the unit cost with the following formula:
Unit Cost = Direct Unit Cost + (Direct Unit Cost * Indirect Cost %) + Overhead Rate.